The project was carried out in 2016, involving 3 objectives within the base. The first involved the execution and the assembly of metal structures at the grain collection pit. The second was the execution and assembly of a metal storage hall.
The project was carried out in 2016, involving 3 objectives within the base. The first involved the execution and the assembly of metal structures at the grain collection pit. The second was the execution and assembly of a metal storage hall.
The third one entailed the execution and assembly of metal structures for the fuel distribution station. A total of 80 tons of metal works were produced and assembled for this project.
The project was developed in Cehu Silvaniei, a town in the northwest part of Romania for a Concentrated and Combined Animal Feeding Operation.